Rockingham Fire Pump Station

Industrial

Project Details

Cooper Tacia was contracted to construct a fire pump station for a 400-acre manufacturing facility.  Our scope included the underground piping, the foundations, the steel structure, the mechanical system, and the electrical systems.  The pump itself was installed by its manufacturer.  The project may look small, but the foundation alone was one of the most reinforced we have ever constructed and cost more than most homes!

Client

Enviva Biomass

Contract Type

Lump Sum

Designer

O’Neal Inc